Walls Arrive

Unload

Rain is coming




The pack distributed around the pad - hopefully where they are needed. !

A 2 hour job to weld up the device to make the job a hell of a lot easier !
First wall in place - our bedroom. 

Friends lend us the platform with stair - Thank you so so much Bron and Dave

These walls on this section are 4.4m tall.

Day 1 - 2.7m on the short side. 1and half walls done! Our bedroom on our fist day !

Day 2 - Our bedroom and the outside wall of the laundry and some of the kitchen.

Day 2 Done

Day 4 North wing 'nearly' done !

Day 4 Done

Day 5 last wall in our room

Door way to our room, looking at the ensuite.

Day 5 Done !